From Scilly Today 20 July 2012.
Scilly’s MP says he won’t ask the Department for Transport to separate the St Mary’s Quay improvement plans from the Penzance scheme.....
……..Andrew George believes that the mainland project is only six months behind St Mary’s but there are concerns that Penzance won’t make the deadline for European grants, which makes up half of the £8m funding. That means the St Mary’s Quay improvements rely on the mainland project succeeding.
See full item here: http://tinyurl.com/btdspz5
Comment.
It is
understood that there are issues with project deliverability and scope as far
as the Penzance Harbour project is concerned.
The terms
of reference for the Penzance project stated that
it should be deliverable within existing permissions and especially the
existing 2009 Harbour Revision Order (HRO). Penzance Town Council’s budget did not stretch to
seeking Legal Council’s advice on the issue (cost circa £5,000) and at the
beginning of the Options Review it was anyway unclear exactly how extensive any
‘wet work’ in the Harbour would be. With
the ‘preferred option’ identified and worked up in more detail Cornwall Council
has sought Counsel’s opinion and the advice is that an HRO is required. The minimum time for a new HRO is 2 years (it is an Act of Parliament).
Given the
political sensitivity of any works on Penzance Harbour
and the likelihood that objectors would seek Judicial Review (again), it would be
reckless for Cornwall Council to proceed if there was an iota of doubt about
the legal basis of the proposed works.
The project schedule for the Penzance Harbour
project (as presented to the DfT on 15 June) is understood to exceed the timeline
for ERDF funding. DfT is relying upon
the ERDF to fund a major part of the project.
The additional need for a HRO just underlines the impossibility of
delivering the Penzance project with ERDF
funding.
There are
also issues with the scope of the Penzance
Harbour work which is
focussed on freight and passenger facilities. Capital dredging was scaled back
due to cost and the issue of sea defence of South Pier excluded from the scope
of the Options Review. Both the dredging
and sea defence issues are important to the operator, apparently more important
than the full passenger terminal which the operator believes is more than is
necessary. The DfT is aware of these
reservations.
The reality
is that the any project at Penzance that
started ‘from scratch’ was high risk because of the limited time available to
work up an entirely new solution with a much smaller budget. Permissions were likely to be a minefield
for an entirely new solution and this is how it has turned out. This
is not the kind of project a parish council is equipped to handle. Fortunately the problem has been identified
at an early stage (if not the earliest possible stage).
We expect
to hear in the next month or two what is happening to the BIH helicopter
service at the end of October. If it is
not continuing at all (a possibility) then the brief for the Penzance project
needs revisiting because it assumes ‘business as usual’ – a summer only ferry
service. Islanders are going to need
more than Skybus for 5 months of the year which is of course what Friends of IOS Transport is all about.
To view Penzance HRO 2009 click below:
To view proposed plans (and see if you think an HRO seems likely given the scope of the current HRO ) click the link: http://tinyurl.com/cpql3td
No comments:
Post a Comment